Dry Contact Relay Kit Installation & Pinout Reference
This page covers everything needed to install Zira's Dry Contact Relay Kit and wire it into your equipment. The kit ships as a four-component system: a PoE gateway, a 2-channel UDP/LAN dry contact relay, a PoE-to-USB-C converter, and the Zira camera. The gateway delivers PoE to the camera path and provides the LAN segment for the relay. Your controls team wires the load side off the relay; Zira handles the trigger logic.
Kit Contents
The kit ships as four components plus accessories. Verify all items against the list below before starting installation. The gateway powers the entire system over PoE; no separate 24V supply is required for the camera path.
PoE Gateway
Eight-port gigabit router with PoE-out on seven ports and a 10G SFP+ cage. Acts as the kit's power source, LAN segment, and uplink to the Zira platform. The camera path is powered via PoE; the relay sits on a standard LAN port.
- 8× gigabit Ethernet, 7× with PoE-out (up to 57V)
- 10G SFP+ for fiber or high-speed uplink
- Quad-core ARM, desk or rack mount
2-Channel Dry Contact Relay
Two independent SPDT dry contact outputs controlled over UDP/IP. Provides COM, NO, and NC terminals per channel for flexible wiring into existing PLC inputs, alarms, or interlocks. Sits on the gateway LAN; Zira sends triggers as UDP packets.
- SPDT contacts, 10A @ 240V AC / 15A @ 24V DC
- UDP/IP control, static or DHCP configurable
- Screw-terminal load wiring
PoE-to-USB-C Converter
Splits PoE into power and data for the Zira camera over a single USB-C cable. Eliminates a separate camera PSU and keeps the cable run from the gateway to the camera under one jacket. Plugs into any of the gateway's PoE-out ports.
- Input: 802.3af/at PoE, RJ45
- Output: USB-C (power + data)
- Compact inline form factor
- Status LED for PoE link
Zira Vision Camera (USB-C)
Single-cable USB-C camera for the detection event. Powered and uplinked through the PoE-to-USB-C converter; no separate supply needed. Mounted by your install team to view the trigger zone per the use case being deployed.
- USB-C, power + data on one cable
- Industrial mount, M6 thread
- Detection runs on-camera; events sent to Zira
- Field of view per use case spec sheet
Patch gateway port 1 into the customer's switch or wall internet outlet — this is the WAN uplink for the kit. Then run CAT5e/CAT6 from gateway port 3 to the relay's RJ45 jack (data only, no PoE required), and a second CAT5e/CAT6 from gateway port 8 (PoE) to the PoE-to-USB-C converter. Finish with a USB-C cable from the converter to the camera. Keep the camera leg under 3m for reliable USB-C operation.
WAN Uplink & Firewall Whitelist
The gateway needs outbound internet access through the customer's network. Patch gateway port 1 into the customer's switch or wall internet outlet, then have IT whitelist the domains below so Zira services, live video streaming, and camera time-sync can reach their endpoints.
| Service | Domain | Protocol & Ports |
|---|---|---|
| Zira services | *.zira.us | TCP 443 |
| Amazon · live video | *.amazonaws.com | TCP 443, TCP 8883 |
| Amazon · live video | *.amazoncognito.com | TCP 443 |
| Amazon · live video | *.chime.aws | TCP 443, UDP 3478, UDP 5000–65000 |
| Camera time sync | time.google.com | UDP 123 (NTP) |
If the firewall blocks any of the above, the kit will come online but live streaming, dashboard
telemetry, or camera time-sync may fail. The wildcard *.chime.aws UDP range (3478 and
5000–65000) is required for the WebRTC media path used by live video; many corporate firewalls
block these by default. Share this table with the customer's network admin alongside the install
scheduling email.
Front Face & Indicator Legend
Before mounting, identify the indicator zones on the front face. The board has four zones: channel LEDs, system LEDs, power input, and the network jack. Status colors mean the same thing across all eight channels.
Channel LED solid green = relay closed. LED off = relay open. PWR solid = 24V healthy. LINK solid = uplink to Zira platform established. SYNC blinking = receiving live triggers. FAULT amber indicates an over-temperature, short, or firmware error and requires inspection.
Terminal Pinout (Underside)
The screw-clamp terminal block sits along the bottom edge of the enclosure. Sixteen positions: two terminals per channel labelled COM and NO. Wire your load between COM and NO. Polarity does not matter for the relay contacts themselves.
Pin numbering is sequential: pin 1 = CH1 COM, pin 2 = CH1 NO, pin 3 = CH2 COM, and so on through pin 16 = CH8 NO. Use ferrules on stranded wire above 18 AWG to prevent strand fraying. Always de-energize the load circuit before wiring.
Mount the Board, Bring Up the PSU
The board mounts to standard 35mm DIN rail (EN 50022). Place it inside your existing control enclosure beside your PLC, or use a small NEMA-rated enclosure of your own. Provide 24V DC from either the supplied DIN PSU or your facility's existing 24V control bus.
-
1Snap the relay board onto the DIN railHook the top of the enclosure's rear clip over the rail and press the body downward until the spring-loaded lower clip seats. Add an end stop on each side. The board can be mounted in any orientation; allow
20mmclearance above for terminal access. -
2Mount the 24V DIN PSUSnap the supplied PSU onto the same rail. Wire 100-240V AC mains into the PSU's
L,N, andPEterminals using the facility's branch circuit conductor. PSU rating:24V DC · 2.5A. Skip this step if powering from an existing 24V bus. -
3Wire 24V to the relay boardRun two conductors from PSU output (or 24V bus) to the relay board's
24V DC INblock. Use the marked + and − terminals. Recommended 16-18 AWG. Ferrules required on stranded conductors. -
4Energize and confirmApply mains. The
PWRLED should illuminate solid green within two seconds. If PWR is off, FAULT lights, or any channel LED is unexpectedly on, see the troubleshooting section in the quick start guide.
Only a qualified electrician should connect 100-240V AC mains to the supplied PSU. Follow your facility's lockout/tagout procedure before opening any energized panel. Earth/PE termination is mandatory on the PSU input side.
Three Common Wiring Scenarios
The dry contact closes between COM and NO when triggered by the camera. How you wire the load depends on what the load is. Three common scenarios are shown below: a PLC input, a 24V stack light, and a 120V AC alarm or solenoid.
Solenoids, contactor coils, motors, and other inductive loads generate voltage spikes when the relay opens. Install a flyback diode (DC) or an RC snubber (AC) across the load to protect the relay contacts. Without protection, contact life is significantly reduced.
Connect the Board to the Zira Platform
The relay board joins the same network as your Zira cameras. Once it has a link, Zira's installation engineer pairs it to your camera fleet in the platform and configures which detections fire which channels.
-
1Connect the uplink cablePlug the supplied CAT6 patch cable into the
UPLINKport on the board, and the other end into your switch or PoE injector. The board accepts standard 100/1000 Mbps Ethernet. Optional: power the board over PoE+ instead of the DIN PSU. -
2Wait for the LINK and SYNC LEDs
LINKgoes solid when Ethernet is up.SYNCbegins blinking within 60 seconds, indicating the board has registered with the Zira cloud. IfSYNCdoes not blink, check that outbound HTTPS to*.zira.usis permitted on the network. -
3Note the device IDA 6-character device ID is laser-etched on the front face below the model label. Provide this ID to your Zira contact so they can pair the board to your camera fleet in the platform.
-
4Zira configures the trigger logicYour Zira engineer maps each channel to a detection rule: which camera, which event, which dwell time, and which output behavior (pulse, hold, latch). Customer side: provide the channel assignment list to your controls team for documentation.
Test Each Channel Before Going Live
Before connecting the relay's output to a production machine, test each channel in isolation. Zira provides a test mode in the platform that lets you manually fire any channel to confirm wiring without triggering a real detection event.
-
1Open Test Mode in the Zira consoleIn the Zira platform, navigate to
Devices → Relays → [Your Board]and clickTest Mode. This pauses live triggers and unlocks manual channel control. -
2Manually fire each channelClick each channel's
Firebutton one at a time. Verify three things: the front-face channel LED illuminates, the corresponding load activates, and the channel releases when the test button is released or the timer elapses. -
3Check end-to-end latencyTest Mode reports the round-trip latency in milliseconds. Healthy values are under 200ms from console click to relay close. Latency above 500ms typically indicates a network bottleneck and should be investigated before going live.
-
4Exit Test Mode and go liveClick
Exit Test Mode. The board resumes normal operation. Your first real detection trigger should appear in the activity log within seconds of the next configured event on the floor.
If any channel ultimately drives a safety-adjacent device (an alarm in a hand-in-zone use case, for example), test the full chain with the load disconnected first. Confirm the camera detection fires the relay reliably across at least 50 events before wiring to the actual safety circuit.
Bill of Materials
Everything that ships in the kit. Customer-supplied items (AC outlet for the gateway, branch-circuit conductors, load-side wiring beyond the relay terminals) are listed at the bottom for completeness.
| Item | Description | Part ID | Qty | Source |
|---|---|---|---|---|
| 1 | PoE gateway, 8× GbE, SFP+ | ZRY-GW-MTK | 1 | Zira |
| 2 | 2-channel dry contact relay (UDP/IP) | ZRY-RLY-2CH | 1 | Zira |
| 3 | PoE-to-USB-C converter (camera path) | ZRY-PoE-USBC | 1 | Zira |
| 4 | Zira Vision camera, USB-C | ZRY-CAM-V1 | 1 | Zira |
| 5 | CAT5e/CAT6 patch cable, gateway port 3 → relay (3m) | ZRY-PCH-LAN3 | 1 | Zira |
| 6 | CAT5e/CAT6 PoE patch cable, gateway port 8 → converter | ZRY-PCH-POE | 1 | Zira |
| 7 | USB-C cable, converter → camera (1.5m) | ZRY-USB-C15 | 1 | Zira |
| 8 | Ferrule assortment, 22-14 AWG (relay load terminals) | ZRY-FRL-ASR | 1 bag | Zira |
| 9 | Quick start guide and wiring diagram card | ZRY-QSG-RY1 | 1 | Zira |
| 10 | AC outlet / branch circuit feed for the gateway | customer | a/r | Customer |
| 11 | Load-side wiring from relay to PLC / alarm / interlock | customer | a/r | Customer |
| 12 | Flyback diodes or RC snubbers (inductive loads only) | customer | a/r | Customer |
With the board mounted, powered, wired, paired, and verified, the kit is fully installed. For questions during install, reach sales@zira.us or call 650-701-7026. Your Zira contact can also remote-walk through trigger configuration in the platform.